NCDOT Outer Loop Update

The NCDOT held an public drop in session for the purpose of updating residents on the Fayetteville Outer Loop.  The outer loop will create a route around the City of Fayetteville and provide access to I-95.

Project Schedule:

Section – All American Freeway (UNDER CONSTRUCTION)

Section – Cliffdale Road to Canopy Road (UNDER CONSTRUCTION)

Section – US 401 to Cliffdale (RIGHT OF WAY IN PROGRESS)

Section – Camden Road to US 401 (RIGHT OF WAY IN PROGRESS)

Section – I95 to Camden Road (RIGHT OF WAY ACQUISITION BEGINS IN 2018)

To View the Outer Loop handout click the link below

2016ncdotouterloop

For Additional Information Contact:

Mr. Randy Wise, PE
District Engineer
PO Box 1150
Fayetteville, NC  28302-1150
(910) 486-1496
[email protected]

Mr. Joe Bailey, PE
Division 6 Planning Engineer
PO Box 1150
Fayetteville, NC  28302-1150
[email protected]

Print Friendly, PDF & Email