Fayetteville City Council – Park Bond Update

On January 3, 2017, Michael  Gibson (Fayetteville/Cumberland Parks & Recreation Director) gave an update on Phase 1 of the Parks Bond Issuance.

Senior Center West

  • Land located adjacent to Lake Rim along Raeford Road
  • Lease of Land request presented to N.C. Wildlife Board of Commissioners on December 8

Skateboard Park

  • Land Acquisition discussion scheduled for January 11, 2017
  • Proposed site is located on Russell Street and currently owned by A & R Railroad
  • Construction is scheduled to begin in FY18

Splash Pads – Construction Schedule

  • Kiwanis Recreation Center – FY17
  • Cliffdale Recreation Center – FY17
  • EE Miller Recreation Center – FY17
  • Massey Hill Recreation Center – FY17
  • Gilmore Therapeutic Center – FY18
  • Myers Recreation Center – FY18
  • Downtown Baseball Stadium – FY18